Regional Water Development and Conservation Plan Stakeholder Advisory Committee Work Plan Timeline

April 20, 2005

  • Discuss Work Plan through October 15
  • Status on Backlog and Questionnaire Mailing
  • Discuss Draft Plan ("Strawman")
  • Conservation Elements for Inclusion in Draft Plan

May 26, 2005

  • Review Revised Strawman
  • Discuss Baseline Criteria for Surface Water Model
  • Review Technical/Historical Sections of Draft Plan
  • Introduction/Background on Groundwater Model

June 27, 2005 – full day meeting

  • Presentation/Discussion of Groundwater Model
  • Review Revised Strawman

July 2005 – full day meeting

  • Questions/Issues on Groundwater Model
  • Relation to Surface Water Model
  • Review Draft Strawman for Additional Subareas

August 2005 – full day meeting

  • Review Revised Strawman
  • Begin Discussions on Legislative/Rule-making Recommendations

September 2005 – full day meeting

  • Finalize Legislative Recommendations
  • Final Comments and Review of Draft Plan

October 2005 – First Week

  • Review of Final Draft Plan Prior to Public Distribution

October 2005 – Second Week (No Later Than Friday October 14, 2005)

  • Final Plan Due to DNR Board and Out for Public Comment