A Branch of the Georgia Environmental Protection Division

Procedures for Significant Modification without Construction

  1. Permit modification application must be submitted to EPD via GEOS. The application must consist of at least the following completed sections:

    • A - General Information
    • B - Contact Information
    • C - J Any other sections that pertain to changes being made. 

 

  1. The public has a 30-day comment period.
  2.  EPA has a 45-day review period which begins at the end of the public comment period.
  3. The application must include a description of the change, the emissions resulting from the change, and any new applicable requirements.
  4. The applicant may submit a "suggested permit.

Https://geos.epd.georgia.gov/GA/GEOS/Public/GovEnt/Shared/Pages/Main/Login.aspx