Georgia Power Plant Scherer CCR Landfill Permit Information
- Original Permit - May 9, 2023
- Minor Modification 1 rain tarps & evaporators - February 22. 2024
- Minor Modification 2 Cell 2 stockpiles & Cell 3 grading - February 25, 2025
- Minor Modification 3 Cell 3 blasting - September 12, 2025