Air Permit Fees
EPD made changes to Air Permit Fees in State Fiscal Year 2021. Fees were updated to $2,100 per year for Synthetic Minor sources, $1,900 per year for NSPS sources, and the addition of a new Part 70 maintenance fee of $650 per year. Fees have remained unchanged since.
Continue further below for more information regarding your facilities permit fees and how to calculate them.
There are three types of fees associated with Air Permitting in Georgia:
- Air Permit Fees (longstanding annually assessed fee program – see Annual Permit Fees below)
- Expedited Permit Application Fees (optional – see Expedited Permitting)
- Permit Application Fees
Permit Application Fees
Georgia EPD – Air Protection Branch continues to collect annual permit fees and optional fees for expedited permit applications. Beginning March 1, 2019, the Air Protection Branch started collecting permit application fees for each permit application submitted. The fee amount varies on the type of permit application. Some permit applications will not have a fee. Effective March 1, 2021, permit application fees increased as shown in the table below.
Permit Type |
Application Fees |
---|---|
Generic (Minor or Synthetic Minor) Permit |
$0 |
Title V Renewal |
$0 |
Off-Permit Change Request |
$0 |
No Permit Required Exemption |
$0 |
Minor Source Permit or Amendment |
$500 |
Name / Ownership Change |
$500 |
Permit-by-Rule |
$500 |
Synthetic Minor Source Permit or Amendment |
$2000 |
Title V Minor Modification with Construction |
$4000 |
Title V Minor Modification without Construction |
$4000 |
Title V Significant Modification with Construction |
$4000 |
Title V Significant Modification without Construction |
$4000 |
Title V 502(b)(10) Permit Amendment |
$4000 |
Major Source Permit not PSD or 112(g) |
$4000 |
PSD Permit |
$15,000 |
112(g) Permit |
$15,000 |
General Instructions for Permit Application Fees
- Do not submit payment until prompted by Air Protection Branch staff after application submittal.
- Use GECO system to create an invoice and submit along with payment.
- Preferred method of payment is check to P.O. Box 101713, Atlanta 30392 (it is on the GECO invoice); credit card payments must be processed by contacting Lydia Davis at (470) 524-2613.
- For more information, see the Air Permit Fee Manual below, or call the Air Protection Branch – Permitting at (404) 363-7000.
Annual Permit Fees
For calculating fees due for the calendar years 2009 through current year refer to the Air Permit Fee Manual below for the appropriate year. To obtain a copy of the permit fee manual for 1991 through 2008, contact the Air Protection Branch at (404) 363-7000. Only those matters relating to the calculation of air permit fees required under 391-3-1-.03(9) are contained in the Permit Fee Manual, as the text is not intended to be a restatement or interpretation of emission standards or regulations.
Air Permit Fee Manual Downloads
- Air Permit Fee Manual (For Fees Due Between July 1, 2024 and June 30, 2025)
- Air Permit Fee Manual (For Fees Due Between July 1, 2023 and June 30, 2024)
- Air Permit Fee Manual (For Fees Due Between July 1, 2022 and June 30, 2023)
- Air Permit Fee Manual (For Fees Due Between July 1, 2021 and June 30, 2022)
- Air Permit Fee Manual (For Fees Due Between July 1, 2020 and June 30, 2021)
- Air Permit Fee Manual (For Fees Due Between July 1, 2019 and June 30, 2020)
- Air Permit Fee Manual 2017
- Air Permit Fee Manual 2016
- Air Permit Fee Manual 2015
- Air Permit Fee Manual 2014
- Air Permit Fee Manual 2013
- Air Permit Fee Manual 2012
- Air Permit Fee Manual 2011
- Air Permit Fee Manual 2010
- Air Permit Fee Manual 2009
To further assist you in completing the online fee form, the EPD Financial Unit has made available the fee calculation forms used by the auditors. These forms can be used to assist you in performing the annual fee calculations and should be kept on site for auditing purposes. Do not submit the fee calculation forms.
- Summary of Air Permit Fee Calculations through 2016
- Summary of Air Permit Fee Calculations since 2017
Additional Information on stationary source permitting can be found at SIP Construction & Operating Permit Applications, Synthetic Minor Permit Application, and Title V Permitting.